Production Process and Time Required
1. Design concept or requirements shared by client
1 week
2. Time and Cost Estimate
1 Week
3. Approval on costs and timelines
1 Week
4. Designing
2 weeks
5. Design finalisation
2 weeks
6. Production of prototype (1 ft X 1 ft)
1 week for Hand Tufted, 2-3 weeks for Hand Knotted
7. Shipping of prototype including customs clearance - sent by Express Courier
1 week
8. Approval By Client
1 week
9. Production of rug
As per agreed timelines
10. Packaging and Delivery
1-2 weeks By Air, Longer by Sea